Downtown Auburn Progress December 2021On-site work continues on Downtown Auburn's Municipal Complex and infrastructure for the area. Here's the latest from BM&K Construction & Engineering. Regular updates will be provided as the project progresses.  Every step is taken to ensure compliance  with the plans and specifications.  This  includes but is not limited to: 
    Soil density testingConcrete and materials testingFooting and reinforcing inspectionsPavement testing In addition to  the City of Auburn staff and BM&K supervision, Contour Engineering has been  on site to inspect utility installation and earthwork conditions, as well as  Onsite Monitoring conducting weekly erosion control inspections.  
 Recently  Completed ActivitiesSite:  
    Gravel placementGas line relocated Building: 
    Concrete slab pourWaterproofing    City Hall 
 Current Activities   Concrete Slab on Grain 
Site:  
    Waterline InstallationRoadway widening along Hwy 29Erosion control 
Building: 
    ProcurementSubmittals and shop drawingsUnder-slab plumbingConcrete foundation wallsCMU installation    Full Site 
  202112.png)  City Hall 
Upcoming ActivitiesSite:  
    Final site utilitiesPond A Building: 
    Sallyport foundations and CMUStructural Steel 
For more details about Downtown Auburn's redevelopment activities, subscribe HERE to  receive email updates.  |  
 |  |